On July 28, 2011, City Council approved laneway housing development - for RS-1 and RS-5 Zoned, single family areas only – with the following basic requirements.

  • On lots with minimum 33’ frontage, with open rear lanes, on double fronted streets, or on corner lots with a lane or lane dedication.
  • Laneway houses to be located on the rear 26’ of the property & at least 16’ from the main house
  • Must have at least 1 on-site parking space in the rear yard.
  • Units of 1 – 1 ½ storeys, from 500 sq.ft. on 33’ lots, to a maximum 750 sq.ft. on 50’ or larger lots
  • Rental or Family use only – no strata titling
  • Construction of laneway house does not affect existing house (with or without a secondary suite), & they can be built with a new house without affecting its allowable floor area

Beyond these requirements, the City has a number of additional design guidelines:

  • Quality, Durability & Expression: guidelines to ensure quality of materials, architectural design, environmental sustainability, & building durability.
  • Scale & Massing: guidelines for building envelope/roof design, height & floor area limits, site & building orientation, & general neighbourliness.
  • Privacy & Overlook: regulating location of upper floor windows, exterior stairs, roof decks & balconies etc. – LW house to be non-intrusive to neighbours.
  • Lane Frontage: designs must enhance laneways, making them public spaces, like “streets”.  Rules govern lighting, door/window, parking, landscape, garbage location.
  • Landscape: must enhance lane appearance,  environmental performance of the property, & privacy for adjacent properties.

A comprehensive PowerPoint presentation for this is online at vancouver.ca

Before building a laneway house, there are 3 critical first steps1. ensure the property is correctly zoned (RS-1 or RS-5):  2. ensure minimum site width of 33’ & a rear lane: 3. ensure there are services (water, gas, sewer) available for the project –Vancouver Engineering Dept is a great help here. 

Laneway houses were originally promoted as simple projects, with a simple approval process - but they’re not.  The current approval process is like a “mini” development permit application, with complicated conditions & details that must be worked out with a City planner.  A few Laneway house approvals have now been granted, and the following process takes about  6 - 8 weeks,

  • Preliminary meeting with City planner for Design review: 2 weeks for an appointment
  • 2nd appointment to make the Permit application: 2-3 weeks for this appointment
  • Building permit approval  3-4 weeks. 

For most people, that’s many weeks of frustration, worry and time wasted, so it is wise to hire a competent designer/architect to get through City Hall. After the first projects are built & well received by the public, the process may become more streamlined - or not.  The bureaucracy was inevitable, however, and a small price to pay to allow these long-awaited, practical additions to the Vancouver real estate landscape!  For more info on this, contact me, or make enquiries at 604-873-7611.

Newsletter

Sign-up to receive Bob Bracken's Real Estate Investment newsletter.

*indicates required fields.
Name:*
Email:*

Click here for Bob Bracken's Real Estate case studies

  looking at buying
  home
  past client
  Contact Me
Reciprocity Logo The data relating to real estate on this website comes in part from the MLS® Reciprocity program of either the Greater Vancouver REALTORS® (GVR), the Fraser Valley Real Estate Board (FVREB) or the Chilliwack and District Real Estate Board (CADREB). Real estate listings held by participating real estate firms are marked with the MLS® logo and detailed information about the listing includes the name of the listing agent. This representation is based in whole or part on data generated by either the GVR, the FVREB or the CADREB which assumes no responsibility for its accuracy. The materials contained on this page may not be reproduced without the express written consent of either the GVR, the FVREB or the CADREB.